To create a SvcV-8 diagram



Create new Version Of Configuration

To create new Version Of Configuration in SV-8 diagram


  1. Click the Add New button and select Version of Configuration.
  2. Type the name of the newly created Version of Configuration.

Define the resource for the Version Of Configuration

To define the resource for the Version Of Configuration


  1. Right-click the Version Of Configuration in the diagram pane and select Resource.
  2. In the Select Resource dialog do one of the following:
      
    • Select an existing resource that has milestones defined.
    • Create new resource (described in the following procedure).


To create new resource for the Version Of Configuration


  1. In the Select Resource dialog switch on the Creation Mode.
  2. Select package where you want to create a resource.
  3. Click the Create button, choose a resource category Security, Resources, or Operational, and select the desired resource.

  4. In the Specification window of the newly created resource, type its name.

Specify Actual Project Milestones of the resource


Each resource must have two Actual Project Milestone properties defined:

  • Version Released At Milestone (defines the start of a period, Kind - InService).
  • Version Withdrawn At Milestone (defines the end of a period, Kind - OutOfService).


To specify Actual Project Milestones of the resource


  1. In the Specification window of the newly created resource, specify:
     - the Version Released At Milestone property
    .
    Click Edit to open the Select Actual Project Milestone dialog and do one of the following:
     - the Version Withdrawn At Milestone property. Click Edit to open the Select Actual Project Milestone dialog and do one of the following:
  2. Click Close > OK. 
    The Actual Project Milestone is specified.

To create new milestone with kind In Service


  1. In the Select Actual Project Milestone dialog, switch on the Creation Mode. 
  2. Select package where you want to create an Actual Project Milestone.
  3. Click Create. 

  4. In the Specification window of the newly created Actual Project Milestone specify three properties:
    1. Name. Type a name of the Actual Project Milestone.
    2. Start Date. Define the start of a period. Select the Date property value cell and click Edit. In the Date and Time Settings dialog choose a date and click OK.
    3. Kind. Select the Kind property value cell an choose a milestone kind: In Service.

     
  5.  Click Close > OK.

 

To create new milestone with kind Out Of Service


  1. In the Select Actual Project Milestone dialog, switch on the Creation Mode. 
  2. Select package where you want to create an Actual Project Milestone.
  3. Click Create. 

  4. In the Specification window of the newly created Actual Project Milestone specify three properties:
    1. Name. Type a name of the Actual Project Milestone.
    2. Start Date. Define the end of a period. Select the Date property value cell and click Edit. In the Date and Time Settings dialog choose a date and click OK.
    3. Kind. Select the Kind property value cell an choose a milestone kind: Out Of Service. 

  5.  Click Close > OK.

 

The result of this procedure is as the following figure.