To create a SvcV-8 diagram
Create new Version Of Configuration
To create new Version Of Configuration in SV-8 diagram
- Click the Add New button and select Version of Configuration.
- Type the name of the newly created Version of Configuration.
Define the resource for the Version Of Configuration
To define the resource for the Version Of Configuration
- Right-click the Version Of Configuration in the diagram pane and select Resource.
- In the Select Resource dialog do one of the following:
- Select an existing resource that has milestones defined.
Create new resource (described in the following procedure).
To create new resource for the Version Of Configuration
- In the Select Resource dialog switch on the Creation Mode.
- Select package where you want to create a resource.
- Click the Create button, choose a resource category Security, Resources, or Operational, and select the desired resource.
- In the Specification window of the newly created resource, type its name.
Specify Actual Project Milestones of the resource
Each resource must have two Actual Project Milestone properties defined:
- Version Released At Milestone (defines the start of a period, Kind - InService).
- Version Withdrawn At Milestone (defines the end of a period, Kind - OutOfService).
To specify Actual Project Milestones of the resource
- In the Specification window of the newly created resource, specify:
- the Version Released At Milestone property. Click to open the Select Actual Project Milestone dialog and do one of the following:- Select an existing milestone defined with kind In Service.
- Create new milestone (described in the following procedure "To create new milestone with kind In Service").
- Select an existing milestone defined with kind Out Of Service.
- Create new milestone (described in the following procedure "To create new milestone with kind Out Of Service").
- Click Close > OK.
The Actual Project Milestone is specified.
To create new milestone with kind In Service
- In the Select Actual Project Milestone dialog, switch on the Creation Mode.
- Select package where you want to create an Actual Project Milestone.
- Click Create.
- In the Specification window of the newly created Actual Project Milestone specify three properties:
- Name. Type a name of the Actual Project Milestone.
- Start Date. Define the start of a period. Select the Date property value cell and click . In the Date and Time Settings dialog choose a date and click OK.
Kind. Select the Kind property value cell an choose a milestone kind: In Service.
- Click Close > OK.
To create new milestone with kind Out Of Service
- In the Select Actual Project Milestone dialog, switch on the Creation Mode.
- Select package where you want to create an Actual Project Milestone.
- Click Create.
- In the Specification window of the newly created Actual Project Milestone specify three properties:
- Name. Type a name of the Actual Project Milestone.
- Start Date. Define the end of a period. Select the Date property value cell and click . In the Date and Time Settings dialog choose a date and click OK.
Kind. Select the Kind property value cell an choose a milestone kind: Out Of Service.
- Click Close > OK.
The result of this procedure is as the following figure.